Pallet flow and AMR handover for a regional DC
Pallet conveyors, a stretch-wrap station and a handover point where autonomous mobile robots take over from forklifts.
Client
Northgate Distribution
Duration
9 weeks
Scope
Conveyors · AMR fleet · WMS link

1,900
pallets per day
0
forklift crossings at the dock
9 weeks
from order to go-live
The challenge
Forklifts and people shared the same dock lane, and the busiest hour regularly ended in near misses.
What we built
A pallet conveyor loop from the dock to a wrap station, with fixed handover points where mobile robots pick up and deliver to the racking.
- Traffic rules agreed with the safety team on paper first
- WMS messages for every pallet move
- Night-time installation, zero lost shipping days
Results
Forklifts no longer cross the dock lane. Throughput is up by a fifth on the same footprint.
Project data
Client
Northgate Distribution
Sector
Intralogistics
Location
Distribution centre
Year
2025
Duration
9 weeks
More projects
Other lines we have commissioned.

Consumer Goods
2026
Panel forming line, rebuilt in eleven days
A 1990s relay-logic forming line moved to modern PLCs, remote I/O and a plant-wide SCADA view without losing a single production week.
+23 pts
OEE, 61% to 84%
11 days
planned shutdown

Automotive & EV
2026
Robot cell for battery tray handling
A six-axis robot now loads formed battery trays into the press line, guided by a camera that checks every part before it moves.
12.4 s
cycle time
2
operators moved to quality roles

Food & Beverage
2025
Filling and capping line for a regional dairy
Filler, capper, labeller and case packer from four vendors, tied into one line controller with a single changeover button.
24,000
bottles per hour
−62%
changeover time
Next step
Planning something similar?
Send us a short description and a few photos of the line. A controls engineer will call you back.